Sweden’s largest onshore wind farm – Havsnäs


Havsnäs Wind Farm is located on three mountain tops north of Strömsund in Jämtland, Sweden. SIC AB has constructed a 30 km road system with crane standings and foundations. The work was done in the period from the summer of 2008 to the summer of 2010. The wind farm is Sweden’s largest wind farm.


Scope:
The project includes 48 turbines with a total effect of 95.4 MW.

Client: NV Nordisk Vindkraft.


First farm constructed in mountain environment – Uljabuouda


Uljabuouda Wind Farm was constructed in a mountain environment in the vicinity of Arjeplog in Norrbotten County in Sweden. SIC AB took over the completion of the road system with new establishment of crane standings and foundations. The work was completed in the summer of 2009. The project was the first large wind farm to be constructed in a mountain environment.


Scope:
The project includes 10 turbines with a total effect of 30 MW.
Client: Skellefteå Kraft.


Hedboberget – Stages I & II


Hedboberget Wind Farm, Stages I and II, is located in Furudal in Dalerne County in Sweden and was constructed in two stages. In Stage I, executed in the summer of 2008, SIC AB constructed 8 km of new roadway, upgraded 4 km of existing roadway and established foundations and crane standings. In this project seven of the foundations were established as RockAdapters anchored in the mountain. Stage II is underway and includes six turbines, now with a hub height reaching 105 meters. SIC AB is also constructing a mix of four RockAdapters and two gravitation foundations. The work will be completed during the course of 2010.


Scope:

Stage I includes 9 turbines with a total effect of 18 MW.

Stage II includes 6 turbines with a total effect of 12 MW.

Client: O2 Vindkompaniet.


Extreme bedrock conditions – Svoldrup Kær


Svoldrup Kær Wind Farm is located in Vesthimmerland Municipality, three km south of Farsø in Denmark. SIC A/S has done road and foundation work for six turbines. Roads and crane standings are constructed in field areas where environmental protection and the extremely poor soil conditions have been taken into consideration. During the foundation work it was necessary to drop the ground water level and in that connection all water that was pumped up was purified for ochre before being returned to the natural environment. The work was done in the summer of 2010.


Scope:
The project includes 10 turbines with a total effect of 14 MW.
Client: Wind1.


Selected references in Sweden:

 

Project No. af windturbines Client Constructed
Råshön 7 Vestas 2004
Aapua 7 Vestas 2005
Fjellberget 5 Vestas 2006
Bodberget 1 Triventus 2006
Hedboberget I 9 O2 Vindkompaniet 2008
Bliekevare 18 O2 Vindkompaniet 2008
Bondön 14 Global Gren Energy 2008
Havsnäs 48 Nordisk Vindkraft 2008-09
Gårdsten 1 Kennersys 2008
Uljabuouda 10 Skellefteå Kraft 2009
Simmatorp Skara 3 Svenska Vindbolaget 2009
Fågelås-Hjo 1 Svenska Vindbolaget 2009
Kyrkberget 10 Nordisk Vindkraft 2009-10
Brahehus 9 O2 Vindkompaniet 2009-10
Hedboberget II 6 O2 Vindkompaniet 2010
Granberget 1 O2 Vindkompaniet 2010
Ytterberget 22 Nordisk Vindkraft 2010-11
Nygåedsfjället 11 Nordkraft Vind 2011
Hagesholm 10 Vattenfall 2011


Selected references in Denmark:

 

Project No. af windturbines Client Constructed
Overgaard 10 DONG/Østjysk Vindudv. 2008
Rudmose 4 Wind1 2009
Vognkær 5 Windestate 2010
Svoldrup Kær 6 O2 Vindkompaniet 2010
O2 Vindkompaniet 4 Vattenfall 2010
Lejbølle 3 Wind1 2010